Waterproofing Method Statement in Ghana — Template & Guide (2026)

Waterproofing Method Statement — What It Must Contain

A method statement sets out how the works will actually be done: sequence, materials, environmental limits, hold points, quality records and safety controls. On a Ghanaian project it is also your defence when someone asks, two years later, why the roof leaked.

Use this as a template. Each section below is one you should expect to see — and one a serious contractor will provide without being asked.

1. Project and Scope

  • Project name, location, client and consultant
  • Element being waterproofed and measured area
  • Reference to the specification and drawings
  • Programme dates and working hours

2. Materials

  • Product names, manufacturer and batch traceability
  • Technical datasheets attached
  • GSA certification
  • Safety data sheets
  • Storage requirements on site — temperature, shelf life, out of direct sun
  • Stated dry film thickness the system will achieve

3. Substrate Acceptance Criteria

State the conditions the substrate must meet before anything is applied:

  • Moisture content below 4%, verified by meter and recorded
  • Free of dust, laitance, oil and loose material
  • Falls established, minimum 1:80 to outlets
  • Cracks routed and repaired
  • Substrate temperature within the manufacturer's stated range

4. Surface Preparation

  • Method — wire brushing, grinding, or mechanical preparation
  • Dust extraction
  • Treatment of spalled or contaminated areas
  • Priming — product, coverage, and overcoat window

5. Detail Treatment

The section most often omitted, and where roughly 80% of leaks originate.

  • Parapet and upstand junctions — fleece band width, upstand height minimum 150 mm
  • Drain outlets — collar detail and dressing into the outlet
  • Pipe and service penetrations — collar and sealant
  • Movement joints — banded both sides, debonded over the joint
  • Construction joints
  • Terminations and edge trims

6. Application Sequence

  1. Trial area applied and approved before proceeding
  2. Detail reinforcement completed first
  3. First field coat — stated spread rate, applied in one direction
  4. Overcoat interval — minimum and maximum stated
  5. Second field coat applied perpendicular to the first
  6. Full cure period before trafficking or flood test

7. Environmental Limits

Condition Limit
Substrate moisture Below 4%
Rain forecast No application if rain expected within cure window
Substrate temperature Per datasheet — typically 5–35°C
Working hours Avoid peak surface temperature on dark roofs
Wind Overspray control if spray-applied

8. Hold Points

Work stops for inspection and approval at each of these:

Hold point Why it matters
Substrate acceptance Cannot be verified once primed
Detail reinforcement complete Invisible once field coat is on
First coat before second Confirms coverage and thickness
Membrane before protection layer Last chance before it is buried

9. Inspection and Test Plan

  • Substrate moisture readings — recorded, with locations
  • Wet film thickness checks during application
  • Dry film thickness verification on completion
  • Flood test — duration, depth, and inspection below
  • Photographic record at each stage
  • Non-conformance and corrective action procedure

10. Health, Safety and Environment

  • Work at height — access equipment, edge protection, inspection regime
  • PPE including respiratory protection where required
  • Ventilation for enclosed or internal application
  • Fire precautions — critical for torch-applied systems
  • Waste and container disposal
  • Emergency procedures and site induction

11. Handover Documentation

  • As-built record of areas treated
  • Thickness verification records
  • Flood test certificate
  • Material datasheets and certification
  • Photographic record
  • Warranty certificate and maintenance recommendations

Why This Protects Everyone

If a roof leaks in year two, the method statement and its records answer the only question that matters: was the system installed as specified? Without them the argument is opinion against opinion, and the client usually loses.